Do You Need Building Regulations Approval for a New Roof?

The difference between planning permission and building regulations, when a re-roof needs approval, the insulation rule that catches people out and the certificate to keep afterwards.

By Thomas Hynes, roofing contractor. Last updated 8 October 2026

The short answer

Small like for like repairs usually need no approval. Replacing a whole roof or a large part of one normally does, because it counts as renovating the roof and can require the insulation to be brought up to current standards. Planning permission is a separate question. Always confirm with your local authority.

This guide reflects the rules in England. The other UK nations run their own systems. Your local authority has the final say on any project.

Planning permission and building regulations are different things

Planning permission is about how a building looks and what it is used for. Building regulations are about how it is built: the structure, insulation, ventilation and fire safety. A roofing job can need one, both or neither, which is why so many people are unsure.

Like for like repairs

Replacing a few slipped tiles, refixing a ridge or renewing a section of flashing with matching materials is usually treated as a repair. That normally needs neither planning permission nor building regulations approval. If you are unsure whether your job counts as a repair, ask your local building control team before work starts.

The rule that catches most people out

When a large part of a roof is re-covered, the work is normally treated as renovating the roof rather than repairing it. The figure most often quoted is a quarter of the roof area. Once a job passes that point, building regulations approval is normally needed and the insulation may have to be improved to current standards, where that is technically and economically sensible.

That last point is why a full re-roof often includes new insulation. Ask your roofer whether your job crosses the threshold and how they plan to deal with it.

Other triggers for building regulations

  • Structural changes, such as altering rafters or adding openings for roof windows.
  • A heavier covering, such as swapping lightweight tiles for heavier ones, which may need the structure checking.
  • Changing the roof shape, such as converting a hip to a gable or adding a dormer.

When planning permission comes into it

Most re-roofs with similar materials do not need planning permission. It can be needed when the work materially changes how the roof looks or when the property has extra protection.

  • Conservation areas, where changes to the appearance of a roof can be controlled.
  • Listed buildings, which need listed building consent for most changes, including some repairs.
  • Article 4 directions, which remove some permitted development rights in particular areas.

Your local planning authority can confirm whether any of these apply to your property.

Three routes to building regulations approval

  1. Local authority building control. The council's own team checks and inspects the work.
  2. A registered building control approver. A private body, formerly called an approved inspector, that does the same job.
  3. A competent person scheme. A roofer registered with a scheme for roofing can certify their own work, so no separate application is needed.

The certificate you should receive

At the end of an approved job you should receive a completion certificate from building control or a certificate from the competent person scheme. Keep it with the guarantee for the roof. Buyers' solicitors ask for it when you sell. An insurer may want it after a claim. Our guide on what a roof guarantee covers explains the other document worth keeping.

If work was done without approval

If a roof was replaced without the approval it needed, the local authority can be asked for a regularisation certificate, which may involve opening up parts of the work for inspection. When selling, an indemnity insurance policy is sometimes used to satisfy a buyer, although it does not make the work compliant.

Agree who is responsible for approval before any work begins. Our guide on choosing a roofing contractor includes the questions worth asking. Thinking about a re-roof? Our roof replacement team can talk you through what your job involves. Official guidance is on the Planning Portal. Further topics for homeowners sit in our roofing guidance hub.

Building regulations questions

Do I need building regulations to replace roof tiles?

Replacing a few broken tiles like for like usually does not. Re-covering a large part of the roof normally does, so check with your local authority before work starts.

Who applies for building regulations approval for a new roof?

Either you or your roofer can. Agree who is responsible before work starts and get it in writing.

What happens if my roof was replaced without approval?

You can apply to the local authority for a regularisation certificate. When selling, an indemnity insurance policy is sometimes used instead, although it does not make the work compliant.

Is planning permission the same as building regulations?

No. Planning controls how a building looks and how it is used. Building regulations control how it is built, including structure, insulation and fire safety.